Redcliffe Hospital’s expansion is still moving ahead, but a recent health infrastructure review puts the updated project cost at double what was originally budgeted for it in 2022, with projected completion looking to be in 2030 instead of 2027. The project is part of a state program now being scrutinised for cost blowouts and questionable planning decisions.
Planning Failures Put Redcliffe in the Spotlight
Redcliffe Hospital, located in one of Queensland’s fastest growing corridors, was originally part of a 2022 state-wide health expansion plan meant to boost hospital capacity. But the project is now under scrutiny following the release of a state-commissioned review on 23 April 2025.

The review, led by infrastructure expert Sam Sangster of Klok Advisory, recommends pausing and redesigning the Redcliffe expansion due to poor site layout, clinical planning gaps, and the failure to address a culturally significant scar tree.

The government has accepted this recommendation, committing to a new plan and layout that ensures safer conditions for healthcare workers and a better long-term use of the site.
A Budget Gap Too Big to Ignore
Initially announced in June 2022, the Redcliffe Hospital expansion was budgeted at $1.06 billion, later uplifted to $1.148 billion. However, the latest health infrastructure report places the forecast cost at $2.122 billion, with a funding gap of $1.062 billion.

The plan to deliver 210 new beds and expanded clinical services is still in place, but the timeline has shifted. Originally due for completion in late 2027, the project is now forecast to finish no earlier than the end of 2030. Early works began in July 2024, with Multiplex continuing as the lead contractor.
A Pause, Not a Stop — But Locals Want Clarity
The review found the statewide hospital plan was developed in just six weeks in 2022, prioritising political deadlines over service needs and lacking proper funding.

The project is still expected to deliver more beds and improved care, but the pause and redesign have sparked concerns about delays and rising costs. Locals are questioning whether the region can afford to wait another five years.
Redcliffe and the Road Ahead
While the Queensland government has adopted major recommendations to redesign plans for new Toowoomba and Bundaberg hospital sites, Redcliffe’s project is moving ahead with key design changes to meet local health needs.
It remains part of the state’s Hospital Rescue Plan, aimed at fixing earlier planning flaws and delivering essential infrastructure with stronger oversight.
Early works began in July 2024, and Stage 1 is on track for completion by mid-2025. Locals are watching closely to see if the revised plan can deliver long-promised upgrades without more delays or cost blowouts.
Published 24-April-2025
